🌐 ▾
TroubleAtlas / Tools / Building materials / Concrete Calculator
Atlas Tools 07 · Building Materials

Concrete Calculator

Calculate concrete volume for multiple pours, estimate bags and bulk supplies, and compare alternative costs.

Concrete poured from a mixer truck into a slab
AI-generated photorealistic illustration of a concrete pour.
Quick calculation guide
  1. Select country, currency and measurement system.
  2. Add the elements, dimensions and any non-overlapping voids.
  3. Set the allowance and purchasing options. Enter actual supplier yields and prices.
  4. Check the quantities, compare complete alternatives and print the result.

Changing units preserves quantities and costs. Changing currency requires local prices.

Use internal dimensions of the volume to fill. Avoid counting overlapping elements twice.


Select one or more options. Initial values are illustrative geometry, not specifications or market prices.

Bagged concrete mix
Ready-mix truck delivery
Site mixing — supplied mix proportions

Blank price = unavailable. Enter 0 only for genuinely free items. Unentered optional extra costs are excluded.

Project results
—

Concrete to order, including allowance

Enter dimensions.

First element geometry

​

Pour quantity breakdown

Supply comparison

Quantity and cost estimate, not structural design. Confirm dimensions, specifications, yield, placing conditions and safety with the professional and supplier.

Atlas Technical Guide

Illustrative detail of levelling fresh concrete
AI-generated illustration: surface finishing. Not a safety instruction.

How much concrete do you need?

Calculate the internal volume of the elements, subtract actual displacements and add an allowance for site variations. One cubic metre equals 1,000 litres. The purchased volume can be greater because of full packages, minimum orders or sales increments.

Geometry formulas

Convert all lengths to metres before calculating. L = length, W = width, H = height or thickness, D = diameter. These formulas describe geometric volumes, not recommended structural dimensions.

Slab: V = L × W × H
Strip footing, pad footing, wall, beam: V = L × W × H
Cylindrical column and circular slab: V = π × D² × H / 4
Post hole: V = π × D² × H / 4 − embedded post volume
Solid stairs: V = W × tread × rise × n(n+1)/2

For a round post subtract its circular section multiplied by embedded depth; for a rectangular post subtract width × length × embedded depth. Solid stairs consist of equal solid steps without landings or cavities: a sloping waist slab requires another geometry. Enter known volume for other shapes.

From net volume to order quantity

Net V = Σ [ (gross V per element − void V per element) × quantity ]
Order V = net V × (1 + allowance / 100)

Count only non-overlapping volumes separately. The allowance is a user choice, not a regulatory requirement: assess excavation tolerances, formwork irregularities and expected losses with the contractor. Apply it once. The engine retains internal precision and rounds purchase quantities up.

Quick table: volume by area

Geometric values without allowance for a uniform slab. Thicknesses are calculation examples, not construction specifications.

Volume in m³
Area5 cm10 cm15 cm20 cm
1 m²0.050.100.150.20
10 m²0.501.001.502.00
25 m²1.252.503.755.00
50 m²2.505.007.5010.00

Bags, pallets and actual yield

Cement is a binder; concrete also contains aggregates and water. A bag of pure cement is not a bag of concrete mix. Yield depends on the product formulation: use the manufacturer's declared litres of fresh concrete, not bag weight divided by a generic density.

Bags = ⌈order V / yield per bag⌉
Full pallets = ⌈bags / bags per pallet⌉
Purchased volume = purchased bags × yield

For example, QUIKRETE Concrete Mix 1101 in an 80 lb (36.2 kg) bag declares about 17 L per bag. The Boral Cement 2025 guide specifies 108 bags of its 20 kg Concrete Mix per m³. These are product-specific figures, not universal factors.

Bag counts for hypothetical yields, without allowance
Volume10 L13 L17 L
0.25 m³252015
0.50 m³503930
1.00 m³1007759

Ready-mix delivery: minimum order, delivery and pump

If the supplier requires a minimum, compare it with the requirement. If sold in fixed increments, round the greater value up to the next increment. Estimated loads equal the purchased volume divided by available capacity, rounded up. Confirm actual capacity, site access, timing, small-load charges, waiting time, pump and return costs with the supplier.

Purchased V = ⌈max(order V, minimum) / increment⌉ × increment
Loads = ⌈purchased V / capacity per load⌉
Cost = purchased V × price per m³ + delivery + other costs

If no increment applies, use the greater of the requirement and minimum. Do not confuse drum volume with actual transportable quantity.

For a cost comparison, ask suppliers for premix bag yield, ready-mix price per cubic yard or cubic metre, minimum load, delivery and pump fees. This calculator does not supply local prices automatically.

Site mixing: only specified proportions

Enter the dosage per cubic metre supplied by a professional or applicable technical specification: cement, sand and aggregates in kg/m³, water in L/m³. The calculator multiplies each dosage by the order volume and rounds packages when requested. It does not validate mix yield, water/cement ratio, aggregate moisture, workability, exposure or strength. Do not add water arbitrarily.

Component quantity = dosage per m³ × order V
Packages = ⌈quantity / package capacity⌉

Example 1 — slab and four pad footings

A 6 × 4 m slab, 0.10 m thick, yields 2.40 m³. Four 0.50 × 0.50 × 0.60 m footings add 0.60 m³, assuming no overlap with the slab. With a hypothetical 10% allowance: (2.40 + 0.60) × 1.10 = 3.30 m³.

With a hypothetical yield of 13 L per bag, 254 bags are needed. If pallets contain 48 bags and only full pallets can be bought, 6 pallets are needed: 288 bags, with a declared yield of 3.744 m³.

Illustrative quotations in EUR, not market prices
OptionPurchaseCost
Bags at €5254 × €5€1,270
Pallets at €2206 × €220€1,320
Ready-mix truck3.5 m³ × €150 + €80 delivery€605

The last case assumes a 2 m³ minimum, 0.5 m³ increment, 5 m³ capacity and one load. These costs cover only the listed items: add labour, equipment, handling, any pump and taxes on the same basis for all options. A lower price does not establish technical equivalence.

Example 2 — four post holes

Four cylindrical holes, 0.30 m in diameter and 0.60 m deep, contain round posts 0.10 m in diameter embedded 0.60 m. Per hole: π × (0.30² − 0.10²) × 0.60 / 4 ≈ 0.037699 m³. Total: 0.150796 m³; with 10% allowance ≈ 0.165876 m³. With 13 L bags, you need 13 bags, for a purchased yield of 0.169 m³. Dimensions are illustrative only.

Metric and imperial conversions

Geometric equivalents
UnitEquivalent
1 m³1,000 L ≈ 1.308 yd³
1 yd³0.764554858 m³ = 27 ft³
1 ft³0.028316847 m³
1 in2.54 cm

Changing units must not alter physical volume or equivalent cost. Changing currency requires new local prices: no exchange-rate conversion is performed.

Common mistakes to avoid

  • Using centimetres as metres, or confusing diameter and radius.
  • Counting the shared volume of footings, beams and slabs twice.
  • Subtracting an already deducted void or one outside the element.
  • Confusing kg of dry mix with litres of fresh concrete.
  • Rounding volume before calculating bags and pallets.
  • Forgetting minimum orders, deliveries and equipment costs.
  • Treating missing prices as zero or inferring a strength class from volume.

Frequently asked questions

How many bags make one cubic metre?

Divide 1,000 litres by the declared yield in litres per bag and round up. At 13 L, 77 bags are needed without allowance.

How much concrete for 20 m² at 10 cm thick?

20 × 0.10 = 2 m³ net; with a hypothetical 10% allowance, 2.2 m³.

How much cement is needed per cubic metre?

It depends on the specified concrete mix proportions. The tool does not determine them: it multiplies the supplied dosage by volume.

Can I calculate several pours at once?

Yes, up to 100 elements, with identical-element counts and void volume per element. Avoid overlap.

How do I calculate solid concrete stairs?

For equal solid steps: width × tread × rise × n(n+1)/2. Add landings and other parts separately; do not use this formula for a sloping waist slab.

Is ready-mix delivery always better?

No. Compare availability, yield, minimums, transport, access and placing costs; compare only suitable options and complete quotations.

What allowance should I add?

There is no universal percentage. Choose based on project tolerances and conditions; confirm with your supplier or contractor.

Why is the quotation total missing?

At least one required price is missing. The known subtotal is not the full cost; enter zero only if an item really is free or excluded from the contract.

Does the calculator specify thickness and reinforcement?

No. Enter dimensions specified by the design. Strength, reinforcement, foundations and compliance require professional assessment.

How do I protect skin and eyes from wet cement?

Avoid contact with wet cement and dust; use PPE specified by safety data sheets and site procedures. Wet cement can cause chemical burns. If exposed, follow the safety data sheet instructions.

Method, sources and limitations

The calculator uses Euclidean geometry and SI conversions. Purchase quantities and costs depend solely on inputs. It does not certify design, ground conditions, placement or regulatory compliance. Diagrams and AI-generated images are illustrative, not operating instructions. Check standards applicable to the location and type of work.

Local concrete references

For structural work, confirm the applicable codes, specified concrete and project requirements with a qualified professional. These references are starting points, not a compliance assessment.

Editorial team: TroubleAtlas Technical Team · Updated: . Internal editorial review, no independent structural certification.

Scroll to Top
Privacy settings